Landfill Final Cover Anchored Wall System

12 m high waste face with 3H:1V slope requiring permanent stabilization without excavation

๐Ÿ—๏ธ Project Overview

Closed municipal landfill slope stabilization, Georgia

๐ŸŽฏ Challenge

12 m high waste face with 3H:1V slope requiring permanent stabilization without excavation

๐Ÿ”ง Design Approach

Soil nail wall with corrosion-resistant grouted nails, shotcrete facing, and HDPE drainage mat

๐Ÿ“ Design Diagram

Waste Fill (3H:1V) Soil Nail Wall Shotcrete Facing HDPE Drainage Mat Tult=245 kN Global Stability FS = 1.58 12 m High Waste Face โ€ข No Excavation 12 m 3H:1V Wall Structure Soil Nail Drainage Mat

AI-generated project design illustration

๐Ÿ“ Key Calculations

Nail Pullout Resistance

T_ult = ฯ€ยทdยทฮฃ(ฮฑยทฯ„_fยทL_i)
Result: 245 kN/nail
Exceeded design load by 2.1ร—

Global Stability with Nails

FS_global = ฮฃ(R_i)/ฮฃ(D_i)
Result: 1.58
Met EPA RCRA Subtitle D requirement

๐Ÿ“Š Results

Achieved 100-year design life certification; no nail corrosion observed at 5-year inspection

๐Ÿ’ก Lessons Learned

  • โ€ขGrout chemistry must match leachate pH profile
  • โ€ขShotcrete thickness must accommodate nail head embedment and drainage mat compression

โœ… Key Takeaways

  • 1Grout chemistry must match leachate pH profile
  • 2Shotcrete thickness must accommodate nail head embedment and drainage mat compression